Road No 9 upgrade 62 percent complete
The improvement project to upgrade a 58km section of National Road No 9 in Savannakhet province is now about 62 percent complete, after it was started back in 2012. Head of the Savannakhet provincial Public Works and Transport Deparment, Dr Sengthong Vangkeomany, told the media that work on this project was now already 62 percent complete, but admitted that work had progressed a little slower than projected in the original plans. He was still confident, however, that the project would be completed on time.
The budget for the project was set at 3.273 billion yen, coming via a grant by the Japanese government through the Japan International Cooperation Agency. The project is scheduled to run for three years from April 2012 to March 2015, with the work being divided into two sections. The first phase runs from Atsaphangthong to Phalanxay districts over a length of 47 kilometres and the second from the Xethamourk area to Phin district over a length of 11 kilometres. The work is contracted out to a joint venture between Obayashi Corporation and the Obayashi Road Corporation and is supervised by Oriental Consultants Co Ltd.
Previously the road was of variable thickness which resulted in the creation of potholes due to the passage of large numbers of heavy vehicles. But the new surface will be much thicker, so the road will be able to withstand heavy traffic. National Road No 9 is another important route in terms of the country's socio-economic development. The road links the east and west parts of Laos and is part of the East-West Economic Corridor which is of strategic importance for the region.
Adapted from Vientiane Times
As mentioned earlier... time since rain is important on Route 4B. This was it, in the rain, in 2012. It gets slippery. Very slippery. This next photo, I'd just "spun out"... slid to a stop sideways. The drop there was several hundred feet
Some of the hills are steep. I went down several on that trip with the engine off, bike in gear... both feet down, using the engine for braking. This most recent trip, I lost my rear brake on the descent into the village by the river. PITA. That was my excuse for stopping for the extended massage
So true! Just got a message from a friend that last week (when they had heavy rain for a few days) it took 2 bikers some 8 hours to cover the 120 km. off-road section from Hongsa to Luang Prabang They left one biker behind who, due to exhaustion, could not carry on. They had to send a truck in to pick him and the bike up.
Work begins on the reconstruction of highway 13 North from Pak Mong (Luang Prabang) to Oudomxay
Oudomxay province : Reconstruction of Road No. 13 North between Oudomxay provincial capital to Pakmong in Luang Prabang province's Nambak district is underway following a stone-laying ceremony yesterday in Oudomxay. Chinese Yunnan Sunny Road and Bridge Co., Ltd. (YSRBC), and Third Railway Survey and Design Institute Group Corporation (TSDI) have been contracted to rebuild the 81.5 km section, working with the Ministry of Public Works and Transport.
The deal was inked on December 16, 2012. The US$82.5 million project will have a time frame of three years with Burapha Development Consultant as the supervisor. This is the first ever reconstruction of this section of road from Meuangxay-Pakmong since it was first built in 1976. The road will be constructed to a technically third class standard, while its sub-sections are to have different widths. A 73 km. sub-section from Pakmong to Oudomxay will be 7 metres wide and will have a 5-centimetre thick layer of asphalt. The road will be eight metres wide where it passes through villages. Some sections and connecting roads in Oudomxay provincial capital will be 12 to 18 metres wide and will be able to carry loads of up to 11 tonnes per axle. Sidewalks will also be installed on urban sections of the road.
Adapted from Vientiane Times
UPDATE ON THE UPGRADING OF ROAD 16B FROM XEKONG VIA DAKCHEUNG TO THE VIETNAM BORDER (http://www.rideasia.net/motorcycle-...velopment-road-construction-laos.html#post337)
Xekong road project faces delays
Work on the 212km National Road 16B, linking Xekong province to the Vietnamese border, is facing delays as the construction company waits on its contract to be extended. Project head, Mr Bounchanh Sengdara, said Tonghomsombath Construction Company had signed a four-year contract with the government for the work in 2009, and had recently submitted a request to the government to extend the original contract. “We do not know when the government will allow the project to continue, so work has stopped temporarily,” he said.
While construction of the new road was initially expected to be complete by the end of the year, weather conditions and landslides have caused a number of delays. A late decision to widen the road from 9m to 13m and add sidewalks, lighting and improved drainage through 3km of the Xekong provincial capital also affected the project timeline. Mr Bounchanh said the company could not put a date on completion of the project and may face further delays while the government works on extending the contract. In 2009, the government authorised Tonghomsombath Construction Company to spend more than 370 billion kip (US$44 million) to build the road. That figure increased after the decision was made to widen the road in Xekong. The company is financing the project, with the government to repay the costs over a nine-year period.
Source: Vientiane Times 19 August 2013
Ferry Co ordinates.
It's a short ride & these may change as the water level changes, but not by much as the road will always end at the waters edge.
N21 25.759 E102 20.155
N21 24.832 E 102 20.614
GpxViewer
Highway 14 (A, B, C, A1).
Construction of the new road (Rd 14 A) west of the Mekong from highway 16 (Vangtao to Pakxe) to Champasack (Wat Pou) is going fast and it is expected that in a few months the whole road is asphalt.
Road 1G (Rd 23) to be upgraded and Paved
The construction of 64-km National Road No 1 G South, stretching from Savannakhet border to Nadonekhouang Village, Saravane Province, is planned to be renovated soon.
The project worth a total of 548.6 billion kip, partly financed with a Government contribution approved by the National Assembly in 2012-2013. According to the plan, this road will give access to seven villages of Saravane district and nine villages of Toumlan district, which are scheduled to be paved by asphalt. The renovation work is expected to be completed by next 48 months.
The construction of Road No 1 G is a national priority project, a strategic channel linking the north to the south. This road aims to serve the national defense and security, accessing to remote areas and connecting localities and districts with the central part and neighboring countries. Upon completion this road will spur the growth of economy, society, trade and investment in industry, creating jobs and upgrade living condition of the locals, favoring agriculture and tourism.
The contract for No 1 G road renovation was signed by Saravane Governor Khamboun Douangpanya and President of Douangchaleun Construction Company Group, Mr. Khamphai Silasha in Vientiane, on May 18. Witnesses of the event were the LT Gen. Duangchay Phicith, Deputy Prime Minister and Minister of National Defense, Mr. Sommath Pholsena, Minister of Public Works and Transport and various officials concerned.
Source: :: KPL :: Lao News Agency
Note by LR: The road improvement starts from Rd 15 and goes north up to the provincial border between Saravane and Savannakhet - this would leave the last 20 km. which is very bad (very difficult for cars as well as bikes) from the provincial border to the Xe Banghiang river in its present state.
View attachment 17398
Update on Rd 13 North from Pakmong to Oudomxay
Things are moving fast (the work started in March 2014) and the first 10 Km. on the Oudomxay side are paved while on the Pakmong side the first 17 Km. are paved and the next 10 Km. are in varying stages of being sealed. In some of the villages such as Ban Lak 32 the road has been paved as well. All the old pavement has been taken out and the hard shoulders of the new road are more or less in place along the whole length of the road and it looks like that they are waiting for the dry season to start to continue with building up the roadbed, taking out some of the switchbacks, etc. before putting in more new pavement.
A few pics of the road:
Xekong-Vietnam road link set for completion in 2017
The construction of National Road No.16B linking Xekong provincial capital with Vietnam will be complete in 2017 after suffering a series of delays, an official in charge of the project has confirmed. The 120-km road is being built by two construction companies who have been allocated US$51.5 million of government money to undertake the project. The road passes through Dakcheung, one of the country's 42 districts officially classified as poor, before reaching the Vietnamese border.
Construction of Road No.16B is underway in Xekong province.
Director of the Xekong provincial Department of Public Works and Transport, Mr Soutsana Sihavong, told Vientiane Times on Friday that JICA is funding the construction of a US$15 million bridge across the Xekong River. The bridge is also scheduled for completion in 2017. Construction of National Road No.16B began in 2003 but work was delayed due to financial difficulties. But construction picked up in fiscal year 2014-15 as the government wanted the road to be finished in the same year as the bridge across the Xekong River. Currently only about 20km of the road is paved. Some sections make for treacherous driving as they are very narrow and potholed, as well as passing through mountainous terrain.
Source: Vientiane Times by Somsack Pongkhao - (Latest Update December 21, 2015)
Xe Bangfai Bridge - Rd. 5528
In June 2013 the contract for the construction of a bridge over the Xe Bangfai river in the road (part of the HCM trail) running from Ban Langkhang/Na Phao on Rd. 12 to Boualapha and onwards to Vilaboury and Rd. 9 was signed. According to the contract, the construction work is determined to be completed two years after the signing date (so, if everything goes according to schedule the bridge will be ready in June 2015). The bridge, costing 40 billion kip, is designed to be 181 m long and 10 m wide with a footpath on each side and street lights.
Extracted from :: KPL :: Lao News Agency
This is how the crossing in June 2013 looking north when Johnny and Matt crossed the river when the river was still quite low - just imagine how it will be a few month from now at the height of the rainy season.
The new bridge in Pakse replacing the old "French Bridge" opened yesterday (10 April) and is now open for traffic
The old "French" bridge on the west side of Pakse was a real bottleneck for traffic as it was very narrow and the traffic flow was regulated with traffic lights. This bridge has now been replaced by a new bridge while the road through Pakse has been widened to a 4-lane road. Here are a few pictures of the old bridge - sorry no pictures yet of the new bridge.
View attachment 46752
Traffic on the old bridge
View attachment 46751
Taking down segments of the old bridge
View attachment 46753
Construction of the new bridge
I'd be interested to hear if anyone knows the fate of the village on Route 4B where the major works have been happening. Can't recall the village name, but it's about 2 hours from Luang Prabang, heading to Hongsa.
Here's a couple of shots of the work and the village. I've always stopped there and had a beer, or noodles, or both... on my way through. It just seems to have an ominous look to it all from the air. A couple of drone shots from our last time through, in February.
and the village
A couple more shots of the roadworks on the section of Route 1E from Lak Xao, down past the reservoir to Nakai. My bike took a real hammering on this section in 2012 and I spent 5 days or so waiting for new wheel bearings in Nakai (yeah, yeah... I carry spares now). It won't be long by the look of it and it'll be a stroll in the park
New Laos-Vietnam border checkpoint for Luang Prabang
Work will begin on a new Laos-Vietnam border checkpoint in Luang Prabang province in 2015, moving the checkpoint from the province's mountainous areas to Naluang village in Phonthong district. Luang Prabang provincial Public Works and Transport Department Director, Mr Fasanan Thammavong, told Vientiane Times on Monday the border checkpoint could not be further developed at its present location, about 8km from Nasone village, as the area was too mountainous.
View attachment 20279
Naluang has been selected as the new international border checkpoint as part of a provincial strategy to develop the poverty-stricken village. The village is located in a flatland area, making it suitable for building the water systems, car parks, petrol stations, markets, hotels and transport facilities required at a border crossing. Luang Prabang province shares a border with Vietnam's Dien Bien Phu province. Last Friday, the Lao Ministry of Public Works and Transport signed a memorandum of understanding with its Vietnamese counterpart to build a new road between Luang Prabang's Phouthipheuang and Nasone areas and the Laos-Vietnam border.
The 104.7km road will bypass the centre of Phonthong district to avoid traffic congestion. Transport Engineering Design Inc. of Vietnam (TEID-Vietnam) will work with Luang Prabang provincial authorities to survey and design the new road. Vietnam's Ministry of Transportation will suggest TEID-Vietnam complete the survey by October 15 and submit a report to the two countries' governments. Mr Fasanan said work on the road, which will be constructed with two layers of asphalt, would begin in late 2014 or early 2015, as would work on the new border crossing. Luang Prabang provincial Public Works and Transport official, Mr Khamsy Souvanthong, said the new road would begin at the Road No. 1C junction in Ngoy district and extend to the border. He said main roads in the centre of Phonthong district would be paved with asphalt as part of the project.
Vientiane Times
Will be leaving next week for Laos and might take the 4B on my way to Luang Prabang and, time permitting, will have a look.
Will be leaving next week for Laos and might take the 4B on my way to Luang Prabang and, time permitting, will have a look.
No progress on new Vientiane-Champassak highway
One year has passed but the new Vientiane-Champassak highway survey and design has not progressed following a Chinese company signing an agreement with the Ministry of Public Works and Transport. Recent images posted on social media showing the new impressive Vientiane to Champassak province highway design have caught the public's attention.
View attachment 47060
Road No.13 South connects Champassak province to the capital. (File photo)
An official from the Ministry of Public Works and Transport, who did not wish to be named, told Vientiane Times on Tuesday that a Chinese company signed documents in Vientiane in May last year for the road survey and design. So far the construction company has yet to undertake the work. “We are now writing a letter to the company informing them that if they cannot perform the survey and design then the ministry will announce the cancellation of the project,” he revealed. Normally, construction companies start working on road survey and design within one month after signing with ministry or provincial officials.
The Vientiane-Champassak highway greenfield project will involve construction over a totally new route rather than upgrading the existing Road No. 13 South. Currently, Road No. 13 South, starts at the Dongdok intersection in Vientiane and heads south via Borikhamxay province. Members of the public are wondering why the ministry needs to construct a totally new road along the entire route from Vientiane to Champassak rather than incorporating much of the existing Road No. 13 South into the design.
Meanwhile, a study for a toll-way north of the capital has finished with the ministry assessing the pros and cons of upgrading the arterial highway to cater for the increasing traffic volume. Road No. 13 North may be rebuilt from the Sikeut junction in Vientiane to the bus station in Vangvieng district, a distance of 142 kilometres. Under consideration is a plan to make 57 km of the road, running from the Sikeut junction to Phonhong district in Vientiane province, into a four-lane highway, followed by an 85km two-lane stretch from there to Vangvieng, all of which would be asphalted.
Source: Vientiane Times (Latest Update June 15, 2016) - http://vientianetimes.org.la/
Road 17 B - Muang Sing to Xiengkok and the Laos-Myanmar Friendship Bridge
The final unpaved section of Road No. 17B linking the Laos-Myanmar Friendship Bridge to Luang Namtha province is currently being surveyed prior to asphalt being laid. A 15-kilometre stretch of road links the bridge to Xiengkok village in Long district, of which about 10 km have already been sealed with asphalt. The Laos-Myanmar bridge also links to the Chinese border about 94 kilometres away through Long district.
The bridge, which crosses the Mekong River, is still waiting for the requisite legislation to be passed by Laos and Myanmar before opening to international traffic. At present it is used as an informal border crossing by local people for the sale of goods and personal visits. Authorities hope to open the Laos-Myanmar bridge to all traffic in the very near future so as to benefit from the changes introduced by the Asean Economic Community.
Source: Adapted from Vientiane Times By Khonesavanh Latsaphao, (Latest Update December 29, 2015)
Nice shots. Who's drone took these shots? Did you bring along one or did you google and find this picture online?